Summary of Construction Projects
Director of Maintenance and Operations - Carlos Aluizo

2002 Bond Allocation

The sale of $128,500,000 in bonds was put before voters in September, 2002. Over 80% of voters approved the bond issue. A break-down of how the money will be allocated to improve facilities, enhance technology, and purchase capital outlay equipment is outlined below.

Stephen F. Austin Elementary

Remove and replace existing carpet and vinyl flooring
Complete renovation of public restrooms; new flooring in classroom restrooms
Replace 2 hollow metal doors, side lights; recaulk windows
Install door and frame at entrance to library cave
Replace cabinet doors
Add 4 electrical outlets in classrooms; repair/replace faulty wiring and circuitry in building
Replace galvanized domestic water piping
Total.............................................................................. $511,000
 

A.P. Beutel Elementary School

Renovate the Tally Building
Renovate select boys and girls public restrooms, all teacher restrooms
Upgrade existing air conditioning system
Install ADA Accessible drinking fountains
Replace walkway covers; add additional covered walkway; install new lighting
Replace existing roof systems
Replace damaged carpet
Install new storm drainage; repair or replace gutters and downspouts
Install new entrance foyer
Add 4 electrical outlets to each classroom
Repair or replace walk-in cooler
Replace galvanized domestic water piping
Total.............................................................................. $1,795,000

 

Bess Brannen Elementary

Replace 22 fan coil units; replace library A/C system
Remove and replace existing carpet and vinyl flooring
Install new acoustical lay-in ceiling and lighting
Replace all canopy walkway covers (front)
Renovate classroom into new teacher workroom
Repaint select interior and exterior surfaces
Construct new teacher restroom
Convert storage room into a head-end room (where existing technology wiring is installed)
Replace sealant at windows
Replace all galvanized domestic water piping
Total.............................................................................. $931,000

 

O.A. Fleming Elementary

Replace damaged acoustical lay-in ceiling panels
Install new walkway canopies at cafeteria entrance
Replace damaged air conditioning vents in cafeteria
Replace exterior doors and hardware in the cafeteria
Repair or replace roof on gym and cafeteria
Install new vinyl tile floor in cafeteria
Renovate boys and girls restrooms in cafeteria
Install acoustical lay-in ceiling and lighting in cafeteria
Total.............................................................................. $295,500

 

Madge Griffith Elementary

Construct concrete parking lot for 20 automobiles

Total................................................................................. $40,000

 

Jane Long Elementary

Replace galvanized domestic water piping
Replace all carpet in existing building
Replace the existing air conditioning system
Install new vinyl tile floors
Recaulk exterior windows; replace weather stripping at exterior doors
Install 4 electrical outlets in all classrooms
Refinish stage floor; install new lighting and ceiling system at stage
Construct concrete parking lot for 44 automobiles
Install ventilation systems in boys and girls restrooms

Add fill dirt around building and playground
Install new Universal clock system
Replace 350 l.f. of sanitary sewer at office/main wing
Demolish "B" wing
Build 14 new classrooms and restroom addition
Total........................................................................... $2,311,000

 

Elisabet Ney Elementary

Repaint cracks in exterior and interior brick walls
Install covered walkway to bus drop-off area
Replace toilet fixtures in first and second grade wing; renovate other student restrooms
Replace portion of walkway covers; install lighting
Improve site drainage around perimeter of building
Replace damaged sidewalks around buildings
Replace all carpet
Convert existing stage into general storage
Convert existing cafeteria into a P.E. room
Provide exhaust ventilation in restrooms
Install new covered walkway at front entrance
Replace all galvanized domestic water piping
Build new cafeteria/kitchen, 5 classrooms and restroom addition
Total........................................................................... $2,731,000

 

T.W. Ogg Elementary

Replace acoustical ceiling and lighting in library wing
Construct concrete parking lot for 25 automobiles
Power-clean exterior of existing building
Repaint select exterior surfaces
Install new entrance foyer
Replace galvanized domestic water piping
Replace walk-in cooler/freezers
Install new carpet at front entrance foyer
Install new ceiling and lighting at entrance to "Munchkinland"
Install new carpet in classrooms in "Kansas wing"
Make improvements to electrical wiring and circuitry at "Enchanted Forest and Poppy Field" buildings
Construct corrugated canopy cover at student drop-off
Install ADA acceptable drinking fountains
Total.............................................................................. $839,300

 

Gladys Polk Elementary

Complete renovation of front office/teacher work area
Replace all existing carpet
Install weather-stripping and sealant at each "porthole window"
Install a 3'-0" x 7'-0" door and frame at entrance to library cave
Construct teacher workroom and one pair of teacher restrooms
Add fill dirt around the building to improve drainage
Install new concrete bike rack area
Improve gravel bike paths
Total.............................................................................. $402,000

 

O.M. Roberts Elementary

Investigate concrete slab and make necessary repairs
Replace all existing carpet and vinyl tile floors
Replace blinds in classrooms with mini-blinds
Provide cover plates at gaps in walls
Renovate two pair of restrooms
Replace existing exterior doors
Improve drainage around building and playground
Install acoustical ceiling panels throughout building
Add concrete parking lot for 25 automobiles
Replace kitchen serving line and select storage shelving
Build 4 new classrooms and restroom addition
Total........................................................................... $1,150,500

 

Velasco Elementary

Construct a new campus to house 650 students

Total........................................................................... $7,665,000

 

R. O’Hara Lanier Middle School

Install public address system for Brazosview and Sixth Grade wing
Install fire alarm system for Brazosview and Sixth Grade wing
Build 6 new classrooms, library, cafeteria/kitchen
Renovate Brazosview into 14 classrooms, relocate Fine Arts and convert old library into classrooms
Build 100 parking spaces
Total........................................................................... $4,810,000

 

New Clute Middle School/Intermediate School

Construct new campus to house 500 5th-6th grade students
Construct new campus to house 600 7th-8th grade students
Total......................................................................... $17,547,500

 

Rasco Middle School

Repair and replace blockage in sanitary sewer line beneath parking lot
Convert bookroom into changing room with toilet for Special Education; convert Room 512 to bookroom
Replace deteriorated sheet vinyl flooring in restrooms with ceramic tile
Build 2 new classrooms, new gymnasium, fine arts wing and renovation of existing music room into 4 classrooms
Total........................................................................... $1,896,000

 

Freeport Intermediate

Construct concrete parking lot for 25 automobiles
Construct concrete sidewalk from school to tennis court
Construct 10 concrete visitor parking spaces at front of building
Construct concrete driveway to rear of building
Repaint exterior doors and frames
Rework shower floor in boys dressing room
Reroute condensate line to floor drain next to serving line
Total.............................................................................. $131,100

 

Lake Jackson Intermediate

Construct a new campus to house 1100 7th & 8th grade students

Total......................................................................... $16,573,000

 

Brazoswood High School

Upgrade HVAC system
Construct 4 new science labs
Renovate existing science labs
Construct new concrete parking lot for 75 automobiles
Make modifications to administrative offices
Construct 2 teacher workrooms
Make improvements to cafeteria dining/serving areas
Construct 8 additional classrooms
Upgrade exhaust system at swimming pool
New ceramic wall tile in corridors
Replace existing elevator
Install new acoustical lay-in ceiling and lighting system
Install additional electrical outlets in classrooms
Replace drinking fountains
Repair/replace existing master clock and bell system

Replace all galvanized domestic water piping with copper
Air condition old gym dressing area
Renovate dressing facilities and field house at Wilson Field
Total........................................................................... $9,370,000

 

Brazosport High School

Construct new classrooms and administration area
Construct new cafeteria and kitchen
Install new kitchen equipment and serving lines
Construct main competition gym; renovate 2 practice gyms
New athletic/P.E. dressing area
New roof and renovation to existing athletic area; convert P.E. area to storage facility
Renovate Ag, Music, Vocational buildings; renovate auditorium, lobby
Construct new library and support facilities
Site improvements
Total......................................................................... $21,739,184

 

Alternative Education Placement Center

Renovate existing facility

Total.............................................................................. $750,000

 

District-Wide Projects

District-wide asbestos abatement
District-wide ADA (American Disabilities Act) improvements
Total........................................................................... $1,250,000

 

Transportation Department

Purchase 5 school buses over the next 4 years

Total........................................................................... $1,200,000

 

Career and Technology Education

Purchase capital equipment for vocational programs

Total........................................................................... $1,000,000

 

District-Wide Technology

Upgrade network infrastructure
Upgrade telecommunications
Purchase desktop computers
Upgrade software
Install fiber systems for new schools
Total........................................................................... $8,605,000

 

Athletic Facility Improvements

Replace field house and press box at Hopper Field
Relocate Lions baseball field/stadium to Freeport Intermediate School
Relocate old football field/stadium to Freeport Intermediate School and add 200 parking spaces
Renovate Wilson Field stadium
Repair track at Slade Field
Total........................................................................... $4,500,000

 

District-Wide Band Equipment

Replace aged band equipment

Total.............................................................................. $750,000

 

District-Wide Construction
Inflation and Contingency

Total........................................................................... $8,800,201

 

District-Wide Furniture, Fixtures, Professional Fees, Soil Reports and Material Testing

Total......................................................................... $10,906,715

GRAND TOTAL   $128,500,000